The airport improvement project is coming to a close. The Tilcon company was hired to replace the runway, the taxiway, and all the airport lighting with energy efficient LED lights. They started at the crack of dawn on August 23 immediately following a big storm. They even worked through the hurricane on September 1 to make sure they stayed on schedule.

As of today, they believe they will be finished a day early and that the airport may open on October 20th. Check the NOTAMS!

Runway is closed!

Compass Rose being devoured

Milling in the rain1

Working on the runway

New lights

New signs

Striping the runway