The days are getting longer but it is still cold. If you are not flying much I hope you are getting your plane ready and/or planning trips for later this year. The hangar project is moving along. Be aware planes in hangars and on the ramp will be moving all over the place to accommodate construction crews. But that is a good thing! Constance will be in touch in the months to come regarding who goes where temporarily.
MMK Airport News
The T hangars are almost complete. As of Feb 5th the electrical was almost done. The Certificate of Occupancy is expected the following week. The South Hangar and T Hangars are scheduled for demolition Feb 17th assuming the CO is obtained on time. The last we heard the mid ramp boxes were going in next.